► Hello Sir, I need legal advice regarding a construction agreement issue with AMR Builders. I am from Tiruppur and building my new house at Koduvai. I signed a construction agreement with AMR Builders in February 2026 for ₹31,12,000 at ₹2,000 per sq.ft. I have already paid ₹26,00,000 to the builder. Out of the ₹20,00,000 bank loan, ₹15,00,000 has already been paid to the builder and ₹5,00,000 is still pending from the bank. So, around ₹5,12,000 is still pending under the agreement. The main issue is that the construction is not completed. Only basic/poochi work is completed and many agreed works are still pending. There are also some issues with the completed work. The builder is now saying that he will not do some of the agreed works at ₹2,000 per sq.ft. and is asking for additional money. He is also saying that if I do not pay more, he will keep the remaining work pending. I asked him to complete and hand over the house by 15 October 2026, but the work is not progressing properly. I am ready to pay the balance amount as per the agreement after the agreed work is completed. I do not want to pay extra amounts without proper justification. I have the agreement, payment details, bank loan details, WhatsApp chats, and photos/videos of the construction. Please advise me: 1. Can I legally ask the builder to complete all agreed works at ₹2,000 per sq.ft.? 2. Can he demand extra money beyond the agreement? 3. Can I hold the balance payment until the work is completed? 4. Can I send a legal notice or take legal action? 5. Can I claim compensation for the delay and incomplete work? Please let me know what documents you need. Thank you, Sir.
119 views
2 answers

2 Answers

Sep 27, 2026

Dear Client, 

You can insist that AMR Builders complete all agreed works at ₹2,000 per square feet. He cannot refuse items or reprice them unless the agreement has an escalation or variation clause, and extra payment is justified only for out-of-scope work you approve in writing. Ask him to itemise each disputed item and do not pay extra on oral approval. Moreover, you can hold the ₹5,12,000 balance until the work is completed and defects are rectified, but confirm in writing that you will pay on completion. Since the bank loan is a separate contract, tell the bank in writing that the work is incomplete and ask it to hold the pending ₹5,00,000 disbursement.

Send a legal notice through an advocate by registered post and email, demanding completion and rectification by a stated date, stating the agreement’s completion date if it has one. If he does not comply, file a complaint before the Tiruppur District Consumer Commission within two years, or a civil suit. You can claim compensation for delay, defects, the cost of completing the work through another contractor, interest, harassment and litigation costs. The documents you will need are the agreement with annexures, payment receipts and bank statements, loan documents, WhatsApp chats, dated photos and videos, and the building approval. 

I hope this answer helps, if you have any other query kindly do not hesitate to contact us. Thank you.

Sep 24, 2026

Dear Client,

Under the Indian Contract Act and the Consumer Protection Act, 2019, your builder is legally bound by the terms of the executed construction agreement and cannot unilaterally hike rates, demand extra money beyond the agreed ₹2,000 per sq.ft., or halt work to coerce payment. Since you have already disbursed ₹26,00,000 against incomplete and defective plastering work, you are fully entitled to withhold the pending balance until the milestones are completed as stipulated. You can immediately issue a formal Legal Notice demanding specific performance and handover by the deadline, failing which you may approach the District Consumer Forum or RERA/civil court for completion, rectification, and substantial compensation for delay, mental agony, and deficiency in service. To issue the legal notice and calculate the appropriate claims, we need to inspect your construction agreement, payment receipts, bank loan disbursement schedule, and photographic evidence, for which you may opt for a one-on-one consultation with our office.

Hope this clarifies your position.